ARBITRATION AWARD IN THE CASE OF
THE TIME CHARTER DISPUTE FOR THE S.S. HEISEI MARU*1 (Sample) Authentic Copy *2
Claimant (Shipowner)
With respect to the dispute between the above parties regarding the time charter for the S.S. Heisei Maru dated 20 October, 1990, the following arbitrators, appointed in accordance with Section 15 of the TOMAC Rules, award as follows as a result of serious discussions.
AWARD
FACTS AND ARGUMENTS *5
No. 1 Summary of the Claim and Defence (Claimant)
(Respondent)
No. 2 The Arguments of the Parties 1. Common ground (1) On 20 October, 1990 the Claimant (the shipowner) and the Respondent (the charterer) concluded a 5 year time charter (hereinafter the charter) for the S.S. Heisei Maru ( _________________d/t) (hereinafter referred to as the vessel) owned by the Claimant. The charter hire for the first three years of the charter was to be Yen 25,000,000 per month and the charter hire for the last 2 years was to be determined by the agreement of the parties. (2) Later, citing the actual reduction in freight revenues due to the downturn in the maritime field and the high yen, the Respondent demanded a reduction in the charter hire and after consultation between the parties, as of June, 1993 the charter hire was reduced to Yen 23,000,000 per month. 2. Points in Dispute (Claimant) (1) In the further modification discussions of October, 1993, the Respondent proposed charter hire of Yen 15,000,000 per month, and the Claimant, in light of all the circumstances, was willing to lower the charter hire as low as Yen 20,000,000 per month but no agreement was reached. (2) Accordingly, no agreement was reached and the charter hire remained at the previously agreed amount of Yen 23,000,000 per month, and therefore it was inappropriate when in November, 1993, the Respondent unilaterally wired Yen 16,000,000 into the Claimant's bank account. Consequently the Claimant claimed the difference of Yen 7,000,000 from the Respondent. (3) However,... [following portion omitted] (Respondent) (1)During the further modification discussions in October, 1993, the Claimant indicated an understanding of the circumstances. Although an agreement was not reached in the end, the Respondent nevertheless paid the provisional sum of Yen 16,000,000 which was close to the agreed upon amount. (2) In this way ... [following portion omitted] No. 3. Evidence The Claimant submits Claimant's Exhibits No. 1 to 3, and applies to present Daisuke Amayu as witness. The Respondent submits Respondent's Exhibits No. 1 to 30.
REASONING *6
1. Finding that no written record was made specifying the details of the charter hire modification meeting in October, 1993, the contents of which are the crux of this case, and with regard to which the parties are in dispute................., and that the Respondent was wrong to unilaterally wire Yen 16,000,000 per month into the Claimant's bank account, and further that the Claimant strongly objected to this action by the Respondent (Claimant's Exhibit No. 3), we hereby hold that the Respondent was in breach for failing to pay the charter hire due. 2. However, because the Claimant ......................................................................... 3. On the other hand, as for the Respondent, ......................., not intending to breach the contract, ............................ , from the perspective of...................., etc., we do not recognize the claim of the Claimant with respect to ..................... 4. Regarding the arbitration costs they are Yen_______________________ . With respect to the apportionment of the arbitration costs, as may be surmised from the above, the Respondent was more at fault although neither party was completely without fault, and therefore we hold that the arbitration costs be apportioned at a ratio of 1:2 favoring the Claimant.*7 The arbitrators hereby award as above after due consideration of the totality of the arguments of both parties, the documentary evidence, the hearings of both parties and the testimony of Daisuke Amayu (witness for the Claimant). 20 October, 1998
TOMAC of the JSE
|
TO: The Japan Shipping Exchange, Inc.
RECEIPT
ARBITRATION IN THE MATTER OF THE DISPUTE OVER
THE TIME CHARTER FOR S.S. HEISEI MARU We hereby acknowledge receipt of one authentic copy of the arbitration award in the above-captioned matter. 21 October, 1994 Respondent: Kaisan Bussan Co., Ltd. Attorney Representative: Morio Yamakawa [Signature/Seal] |