(Sample)
ARBITRATION REGARDING THE DISPUTE OVER
THE TIME CHARTER FOR THE S.S. HEISEI MARU
This constitutes notice that, with respect to the
arbitration award for the above captioned matter, both
parties have agreed that they do not want to have the
reasoning for the arbitration award included in the award.
10 October, 1994
|
ARBITRATION AWARD IN THE DISPUTE OVER
THE TIME CHARTER FOR THE S.S. HEISEI MARU (Sample) Authentic Copy*1 Claimant (Shipowner) Muromachi 2-3-16, Nihon Bashi, Chuo-Ku, Tokyo Kofuku Shipping Co., Ltd. Representative: Representative Director Namio Umino Respondent (Charterer) 32 Akashi machi, Chuo-Ku, Kobe, Hyogo-Ken Kaisan Busan Co., Ltd. Representative: Representative Director Sakae Hirano Attorney Representative: Morio Yamakawa As regards the dispute between the above parties over the time charter for the S.S. Heisei Maru dated 20 October, 1990, the following arbitrators, appointed in accordance with Section 15 of the TOMAC Rules, after due consideration award as follows.
AWARD
FACTS AND ARGUMENTS
No. 1 Summary of the Claim and Defence*3 (Claimant)
(Respondent)
No. 2 The Arguments of the Parties *4 1. Common ground (1) On 20 October, 1990 the Claimant (the shipowner) and the Respondent (the charterer) concluded a 5 year time charter (hereinafter the charter) for the S.S. Heisei Maru ( __________________d/t) (hereinafter referred to as the vessel) owned by the Claimant. The charter hire for the first three years of the charter was to be Yen25,000,000 per month and the charter hire for the last 2 years was to be determined by the agreement of the parties. (2) Later, citing the actual reduction in freight revenues due to the downturn in the maritime field and the high yen the Respondent demanded a reduction in the charter hire and after consultation between the parties, as of June, 1993 the charter hire was reduced to Yen23,000,000 per month. 2. Points in Dispute (Claimant) (1) In the further modification discussions of charter hire of October, 1993, the Respondent proposed charter hire of Yen15,000,000 per month, and the Claimant, in light of all the circumstances, was willing to lower the charter hire as low as Yen20,000,000 per month but no agreement was reached. (2) Accordingly, no agreement was reached and the charter hire remained at the previously agreed amount of Yen 23,000,000 per month, and therefore the Respondent was in breach when in November, 1993, they unilaterally wired Yen 16,000,000 into the Claimant's bank account. Consequently, the Applicant claimed the difference of Yen7,000,000 from the Respondent. (3) However,... [following portion omitted] (Respondent) (1)During the further discussions in October, 1993, the Claimant indicated an understanding of Respondent's circumstances. Although an agreement was not reached in the end, the Respondent nevertheless paid the provisional sum of Yen 16,000,000 which was close to the agreed upon amount. (2) In this way ... [following portion omitted] No. 3. Evidence The Claimant submits Claimant's Exhibits No. 1 to 3, and applies to present Daisuke Amayu as witness. *5 The Respondent submits Respondent's Exhibits No. 1 to 30.
REASONING
In accordance with the agreement formed by the parties on 10 October, 1994, we hereby omit the reasoning from this arbitration award.*6 20 October, 1994
|